Confirm the controlled documents
Use the current approved TDS, project specification, drawings, method statement and inspection plan. Confirm the selected CBGM grade and the required strength ages before materials arrive.
Field installation guide
A practical sequence for baseplate and anchor-cage grouting, built from the supplied Sino-sina construction guidance and real site photographs.
Photographed site sequence
Project-party names are not used. The visible work-record overlay is retained only where it documents the construction stage; its identifying fields were already obscured in the supplied image.



Installation sequence
This is screening guidance. A project-specific method statement must resolve geometry, volume, temperature, equipment, sequence and acceptance criteria.
Use the current approved TDS, project specification, drawings, method statement and inspection plan. Confirm the selected CBGM grade and the required strength ages before materials arrive.
Calculate net grout volume from the actual geometry, add the approved contingency, and confirm mixer output, pump capacity, hose route, standby equipment and available labour.
Remove laitance, loose material, oil and standing water. Pre-wet cementitious substrates where required, leave them saturated-surface-dry, and verify that formwork is rigid, sealed and vented.
Calibrate clean mixing water by mass. The supplied CBGM-130 Chinese construction guide records 2.5 kg water per 25 kg bag (about 10%) as its site starting point; the current grade-specific TDS and approved trial batch govern.
Start from the approved inlet and maintain a continuous grout front toward the vent or discharge point. Do not add water to recover lost workability and do not introduce uncontrolled vibration.
Record temperatures, batch times, water, flow and interruptions. Prepare strength specimens to the inspection plan, protect exposed grout immediately and release the next operation only after the required verified strength.
Field records
A traceable grout record links the bag and batch to water, temperature, mixing, flow, placement and strength specimens.
Source document
The supplied Chinese document is dated 19 September 2025 and identifies 中德新亚 as the technical source. It is published here as supporting construction guidance; the current controlled TDS, project specification and approved trial batch remain authoritative for product acceptance.
Technical enquiry
Include the wind structure and connection drawing, geometry or bond line, volume, specified performance, temperature, standards, installation window and equipment.